Buying several electric tricycles is not only about choosing vehicles. Before they join a fleet you need to know where they will charge, how long they stay connected, and how much power is required to have them ready at shift start.
Start with each unit's charger. Its grid draw, multiplied by vehicles charging at the same time, gives a first load estimate. Correct depot sizing also needs other site loads, work hours, and the time window actually available for charging.

Start with the charger datasheet
For each model, get the charger sheet from the manufacturer and confirm at least:
- supply voltage and frequency;
- grid-side current and absorbed power;
- required supply phases;
- expected recharge time for the installed battery;
- compatibility with outlets, circuits, and control systems;
- any limits stated in the manual.
Use grid absorbed power in kW—do not confuse it with battery voltage, Ah capacity, or motor rated power. They are different quantities and cannot alone define charging load.
For eCargo tricycles, battery configuration and the charger actually supplied must be confirmed per trim level. Published battery values alone do not define depot electrical load.
Power for 5, 10, or 20 tricycles?
A first estimate uses a simple formula:
Theoretical peak power = simultaneously active chargers × absorbed power per charger.
Purely illustrative example: assume each charger draws 1 kW from the grid and all units start charging at once.
| Simultaneously connected tricycles | Hypothetical power per charger | Theoretical total power |
|---|---|---|
| 5 | 1 kW | 5 kW |
| 10 | 1 kW | 10 kW |
| 20 | 1 kW | 20 kW |
Active chargers × power per charger = theoretical charging power
Teaching hypothesis: 1 kW per charger (not a eCargo figure)
These are not eCargo specifications and not a sizing proposal. They show how load changes with simultaneous sessions. Use input power from your charger's documentation.
Charging power adds to other depot loads at the same time: lighting, compressors, workshop equipment, HVAC, pumps, and more. Counting chargers alone can understate demand.
Evaluating a fleet? Let's talkYou do not have to charge every unit at once
Fleet size does not always equal simultaneous charging. If return and departure times can be planned, charging can be spread across time bands.
A single-shift operation may use overnight charging. If some units return later or leave earlier, planning must reflect each need.
A reliable schedule needs four inputs:
- how much energy each vehicle must recover after its shift;
- time available before the next deployment;
- power the charger can accept;
- which units need priority because they leave first.
Time bands can lower peak power but not total energy needed for the fleet. If the window is too short, staggering starts is not enough—you may need more available power, a longer window, or different shift design.
To estimate energy each vehicle must recover after a shift, see work tricycle range and autonomy.
Contracted power and what the depot can actually use
Before adding outlets or charge points, review the existing supply and installation.
Contracted power is what the utility makes available under contract. It alone does not say how much can go to charging at every moment—you must account for existing loads, peaks, and panel, line, and circuit limits.
Collect bills, confirm available power, and analyse depot draw in the hours when vehicles would connect—avoid sizing on a theoretical figure that ignores daily operation.
For the definition of contracted power (potenza impegnata) and bill items, ARERA's glossary is a useful reference; use your company's supply contract values in practice.
Scheduled charging or dynamic load management?
A small fleet may only need staggered connection times, if compatible with work and manufacturer guidance. As fleet size or site load variation grows, load management may be worth assessing.
A management system can cap or share power for charging within a defined limit. Dynamic management—when supported by installed hardware—can adjust charger allocation based on building load, using capacity that is actually free rather than assuming peak depot load at all times.
Not every charger can be remote-controlled or integrated with load management. Verify charger, controls, and system compatibility first. A simple plug-in charger does not automatically become smart-charging ready.
General background on charging energy and load management: Schneider Electric — EV charging energy management; Alternative Fuels Observatory — smart charging (PDF). This does not mean every eCargo charger supports those features.
Available power limit (conceptual schema)
Electrical safety: verification before charging
Outlets, circuits, protection, and controls must be assessed by a qualified professional. More wall sockets or adapters are not a substitute for proper design.
Review load power and duration, cable sizing and routing, overcurrent and contact protection, earthing, environment, and charger instructions. Building-related installations fall under applicable rules including DM 37/08 and relevant CEI standards. CEI 64-8 is the general low-voltage reference; whether specific EV-charging rules apply depends on vehicle classification and the installed system.
CEI — CEI 64-8 new edition · Normattiva — DM 37/2008
This article gives preliminary criteria only. It does not replace electrical design, instrumented verification, or sizing by a qualified professional.
Prepare the depot before buying the fleet
Before fixing charge-point count, gather: vehicle count, model and battery, charger datasheet, return and departure times, daily distance, available power, and main depot loads.
Compare scenarios: simultaneous charging, time bands, or load management. The right answer is not always maximum installed power, but availability when needed within site limits and without disrupting other work.
To link grid energy and variable recharge cost, see electric tricycle recharge cost.
Complete planning with charging schedules and total cost of ownership.
You can also use the fleet recharge estimation tool to compare scenarios with charger data confirmed with the manufacturer.
eCargo pages: eCargo Pickup, eCargo Open, eCargo Box.
Request a fleet assessment
Planning several electric tricycles? Bunder can help gather model and configuration data and define what your installer or designer needs to assess depot charging. Tell us fleet size, shift hours, and return times—we start from there for configuration and technical follow-up.
Considering an electric tricycle for your work?
Explore available configurations and find the one that fits your operations.